LithuaniaKaunas
Pumping station process control, automation and electronic communications of heat supply networks

Lithuania, Panevėžys
Installation of 1,5 MW absorption heat pump, condensing scruber

Lithuania, Pravieniškės
Supply, installation, starting-up and adjustment works of 13pcs. gas boiler houses

Poland, Augustów
Supply, installation, starting-up and adjustment works of 8MW biofuel boiler with chamber, condensing economizer and other house equipments (still in progress)

Lithuania, Vilnius
Installation of 2,0 MW absorption heat pump, condensing scruber UAB “Kitimų katilinė“ (still in progress)

Poland, Tomaszów Mazowiecki
Supply, installation, starting-up and adjustment works of  5,1 MW biofuel boiler with chamber, economizer and other house equipments (still in progress)

France / Norway
Electrical design (ATEX) and installation of compressed air, junction boxes and control panels

Poland, Wieluń
Supply, installation, starting-up and adjustment works of  2x 5, MW biofuel boilers with chamber, economizers and other house equipments (still in progress)

Lithuania. Panevėžys
Installation of frequency converters in glass technological lines 

Poland, Tarnowskie Góry
Supply, installation, starting-up and adjustment works of  12 MW biofuel boiler with chamber, economizer and other house equipments (still in progress)