Major engineering projects
SIA Vidzemes energija, Latvia, Gulbene
Construction of the hot water boiler house (installed capacity 4,5 MW; fuel - LPG)
SIA Vidzemes energija, Latvia, Gulbene
Reconstruction of the central boiler house – construction of the water heating boiler house (installed capacity 6,0 MW, biofuel).

Ignalina Nuclear Power Plant, Visaginas
Installation of the heat substations.
UAB „Pramonės energija“, Šilutė
Construction of the steam boiler house (installed capacity 18.000 kg/h steam; biofuel)

Panevėžys district, Ramygala
Construction of the container hot water boiler house (installed capacity 1,6 MW; fuel – natural gas)

2007/2008
|
|
|
JSC "Visagino prekybos centras" ,construction of supermarket
"Domino", 2007/2008 m.: technical supervision of construction.
|
 |
| Production of heat substations modules in Doneckas district,Ukraine |
 |
|
SC „Klaipėdos energija“, Reconstruction and development of boiler
station with steam boilers 10t/h – 2 units construction of Lypkiai boiler house
|

|
|
JSC „Plungės šilumos tinklai“,
Design and installation of a water heating boiler Vitomax 200 LW
(Viessmann, capacity 4,5MW) in the boiler house Nr.1
|
|
2006
|
Rezekne, Latvia
Reconstruction of Nothern and Central boiler houses
Installed capacity – 77 MW
|
|
Construction of JSC "Natūrali oda" factory, Kėdainiai,
2005 -2006m.: technical supervision of construction.
|

|
|
Reconstruction of a mini-clinic of sanatorium
“Versmė”, Birštonas, 2006 project management.
|

|
|
II-nd block reconstruction of sanatorium “Versmė”
Birštonas, 2006-2007:technical supervision of construction and project
management.
|

|
SC "Panevėžio Pienas"
Reconstruction of boiler house
Installed capacity 3,9 MW
|

|
2005

Ignalina "Nuclear Power Plant",
Visaginas Steam boiler house complex
Installed capacity 39 MW
2004
SC "Vilniaus Mėsa", Vilnius
Boiler house
Installed capacity 3,03 MW
2003
JSC "Akmenės Energija", Naujoji Akmenė
Boiler house
Installed capacity 15,3 MW
JSC "Utenos Šilumos Tinklai", Utena
Renovations of boiler house
Installed capacity 14 MW
SC "Lietkabelis", Panevėžys
Reconstruction of energy supply system
8 water heating boiler houses - capacity 1951 kW
Steam generator – capacity 210 kW
Electricity generator – capacity 75 kW
Heating of 7 production shops with gas heating convectors – capacity 1090 kW
SC "Panevėžio Pienas", Panevėžys
Reconstruction of boiler house
Installed capacity 6 t/h steam (3,9 MW)
2002
|
SC "Klaipėdos Kartonas", Klaipėda
Construction of boiler house
Installed capacity 42 t/h steam (31,5 MW)
  
|
|
JSC "Espersen", Klaipėda
Heating system in FEZ
Length of pipeline – 700 m.

SC "Panevėžio Pienas", "Raguva"
Reconstruction of boiler house
Installed capacity 6 t/h steam (3,9 MW)
2001

JSC "Ukmergės Energija", Ukmergė
Assembling of central boiler house
Installed capacity 13,5 MW
VĮ Palangos Reabilitacijos Ligoninė, Palanga
Assembling of cogeneration power plant in rehabilitation hospital
Installed capacity – 120 kW electricity, 1,41 MW heat
2000

JSC "Geoterma", Klaipėda
plant demonstration project
Installed capacity 48 MW
1999


SP JSC "Anykščių Šiluma", Anykščiai
Renovation of district heating network and heat generation
Installed 14 boiler houses with total capacity 42 MW
New heat lines 1,5 km and new gas network 3 km
Installed 130 fully automated heat substations
1998

Akmene Municipality, "Venta"
Renovation of Venta district heating system
Installed 2 boiler houses with total capacity 12,4 MW
4 km of new heat lines
Installed 50 heat substations
1997

Plunge Municipality, Plungė
Renovation of Plungė district heating system
Installed 6 boiler houses with total capacity 7,5 MW